June 2, Day 33 of 45 Day Countdown
Items in bold signify things to do asap!
- Protect refinished floors on first, stairway, and second floor hallway with carpenter paper 
- Remove dust from upstairs bedrooms and bath; lay carpenter paper to reduce dust wherever possible 
- Install kitchen cabinets, plumbing, remaining electricity 
- Complete drywall - doorways, walls (kitchen, dining room, upstairs bathroom, Charlotte’s bedroom), ceilings (dining room, living room) 
- closet/powder room: postpone to after move-in 
 
- Install bathroom — tile floor, bathroom vanity, medicine cabinets, toilet, etc. 
- Complete basement floor epoxy - CP’s office 
- laundry room 
 
- Install doors and molding to one degree or another in all bedrooms, upstairs bathroom, laundry room, basement, stairway, and closet/powder room: postpone to after move-in 
- Retrofit vintage hardwood door with 3/4 lite for front door: postpone to after move-in 
- Install new window in kitchen 
- Build master bedroom closet: postpone to after move-in 
- Landscape as much as possible 
- Do the least amount of harm to ourselves and to the twin! 
- Prime Ceilings and Walls - second floor: master bedroom, office, main bath, hallway, Charlotte’s bedroom, Theo’s bedroom 
- first floor: living room, dining room, kitchen 
 
- Paint Ceilings and Walls - second floor 
- first floor 
 
- Tear down kitchen ceiling 
- Replace kitchen ceiling: why drywall when the newly exposed beams are so gorgeous?